New Headquarter for cms electronics

Current situation report

After long weeks of construction work, the new SMT hall is now ready and cms electronics will start the machine transfer from the old to the new location. A new - the 8th - assembly line has been installed and released for production by our customers.

Also the warehouse is already in use. The next step is the implementation of the AutoStore system, an automated storage system for the reams of components that cms electronics processes every day.

Most of the production-related offices are ready to move in and are waiting for furniture and the necessary IT infrastructure.

The outdoor area and the newly built offices are still under construction. But now in spring with the rising temperatures, work should continue quickly.

According to the management the project "New Headquarter" is on schedule. By autumn this year cms electronics expects full operation at the new location.